  • South Pars Phases 14

     Client: IDRO/ Iran Marine Industrial Co. (SADRA)
     Location: South Pars Gas Field, Persian Gulf
     Project Start Date:  2010
     Scope of Work:  Detail Design, Procurement Engineering
     Brief Description:
    South Pars Gas Field Development Phase 14 shall be developed to produce 2000 MMscfd reservoir from four wellhead platform, separate associated water from the gas and transfer the fluids to the mainland at a distance of 130Km for further treatment.
    Four wellhead platform (Two no. as Main Platform & Two no. as Satellite Platform), designed to produce 600 MMscfd reservoir fluid each. Two 32” sealines of 1 bscfd normal operating capacity will transport the total offshore production to shore. One 18” & One 20” Infield flow line will transfer satellite production to the inlet of the 32” sealine on departure Main Platform deck.

    Two main 4.5” piggy backlines will transport dedicated chemical/inhibitors from onshore to the inlet of the 32” sealines and relevant infield flow lines.



  • pHOTO